The Cassells Street reconstruction project is set to resume on Monday.

The city says the province has said construction projects can continue during the recently announced shut-down of non-essential businesses, with Kenalex providing training to their employees for dealing with COVID-19.

That will include social distancing, cleanliness, disinfection, etc.

All contact between property owners and Kenalex personnel will be minimized using paper handouts, phone calls, and posted notices to City’s website to provide construction updates.

The phase that starts on Monday involves a sanitary sewer being installed next to Chippewa Creek, with flagging personnel on Cassells Street.

In mid-April the road will be closed until early June between King and Chippewa for re-construction work.

This summer, from early June to the end of September will see work on Cassells from Chippewa to Olive, including the Chippewa Creek Bridge.

Phase four, from mid-September to the end of October involves reconstruction of the road from Olive to the bypass.

The final phase which includes paving, landscaping and other work from King to the bypass will take place October 28th to November 15th.

 

Photo by Jeff Turl/BayToday.ca

 

Phases and Dates

Subject to change

Traffic Restrictions Work Description Detour

Route

Phase1a: April 6 to April 17

On right of way adjacent to Chippewa Creek at crossing

Flagging personnel on Cassells St at existing Chippewa Creek crossing Installing sanitary sewer adjacent to Chippewa Creek Yellow – no detour
Phase 1 & 2: April 14 to June 6

From King St to Chippewa St

Cassells Closed to through traffic with local access permitted sewers, watermain, road base, curbs, sidewalks,  asphalt paving Green

and

Magenta

Phase 3: June 7 to Sept 30

From Chippewa St to Olive St

Cassells Closed to through traffic with local access permitted from either side of the bridge. Pedestrians will need to follow detours during this period sewers, watermain, road base, traffic signals, curbs, sidewalks,  asphalt paving, Chippewa Creek bridge Green

and

Blue

Phase 4: Sept 19 to Oct 27

From Olive St to Hwy 11/17

Two Lanes of traffic open at all times. sewers, watermain, road base, traffic signals, curbs, sidewalks,  asphalt paving Black Dash and

Green

Phase 5: Oct 28 to Nov 15

From King St to Hwy 11/17

Two lanes of traffic through Cassells. Delays due to paving & line painting Surface pave entire length of road, landscaping and line painting Combination of detours

 
For project updates check out the City website:
https://www.cityofnorthbay.ca/cityhall/department/engineering/capital-works/cassells-street/